Update: July 10, 2018

Image
Update on the Center for the Arts Even though school's out for the summer, the work on the new Greely Center for the Arts continues in earnest.  Here are a few highlights: All exterior brick work has been completed. The roof has been completed. All windows are scheduled to be installed soon. The concrete interior floor slab has been poured and many of the interior rooms have been drywalled. Connecting corridors between the arts center and GHS have been started. Exterior site work has begun, including rehabbing a water culvert, installing an access road to the arts center, and creating new parking spaces adjacent to the fence across the street from the arts center. Brick & Seat Campaign Update We have officially raised over $25,000 through the Leave Your Legacy Brick & Seat Campaigns for the Greely Center for the Arts. This includes donations from nearly 100 individuals, families and businesses. Thank you to those who have already donated for your gene...